Greeley considers underground boring on pipeline route
By Cherry Sokoloski
North Forty News
Officials from Greeley Water, while moving ahead with plans to install
a 60-inch pipeline through LaPorte, think they have found a solution to
property owners' primary issues with the project.
The city is planning to bore underground, rather than excavating a ditch,
through sensitive areas just south of the Cache la Poudre River. Spokesperson
Dan Moore said preliminary plans call for a series of bores, for a total
of about a quarter mile of pipeline.
The so-called northern segment through LaPorte is just one of several sections
of pipeline that will take water from the city's Bellvue treatment plant
all the way to Greeley. Some of the segments have already been completed,
but the northern segment's preferred route has drawn intense criticism
from some landowners who will be affected.
However, Moore said, the boring method "should avoid most of the concerns
we have heard."
Some of those relate to historic railroad structures such as bridges and
an intact section of track used by the old Greeley, Salt Lake and Pacific
Railroad, which is listed on the National Register of Historic Places.
Property owners have also been irate over possible damage to the geologic
feature called Point of Rocks and irrigation canals in the area.
Moore said that with the boring method, the city should be able to avoid
destroying the historic features and the Point of Rocks. The city would
bore under the irrigation canals and through a ridge just south of the
Point of Rocks. It would go under the old railroad bed at some point, but
the intact tracks would not be disturbed.
Moore said the approach would be friendlier to the environment. The access
road could be smaller, and the area would be easier to restore. The process
would likely involve digging three boreholes, about 20 feet deep, from
which the tunnels would be bored.
There are always surprises when doing underground work, Moore cautioned,
and the city might have to excavate in some areas if they encounter large
chunks of rock.
Mary Humstone, one of the property owners affected by the pipeline route,
said it's too early to say whether the boring method will be an improvement
over trenching.
"We have to have a lot more information before determining the impact on
the historic resource," she said.
Humstone is also concerned about vegetation that will be destroyed by equipment
working on the project. "It's all destructive," she commented.
Moore said that the cost difference between boring and trenching is difficult
to assess. Although boring is a more expensive construction method, restoration
of the property would cost less with that approach. Even with boring, he
said, Greeley is sure that the preferred route on the south side of the
river would be less expensive than the other alternatives considered.
Moore said his office plans to talk with Humstone and her husband, George
Burnette, as well as Jim and Rose Brinks in early February to discuss the
boring process and possible alignments through their properties.
Greeley will also be negotiating for easements with property owners this
spring and summer. There are about 24 landowners along the northern segment
route, Moore said. A private appraiser in Greeley has already completed
her work on land valuation, a starting point for negotiations.
Construction could begin next winter on the project, Moore said, and the
project could take two seasons to complete. The city avoids doing pipeline
work in the spring and early summer because of farming activity, irrigation
and wildlife. Before work can begin, the city must acquire necessary permits
from Larimer County and the U.S. Army Corps of Engineers. The Army Corps
will consult with the Colorado Historical Society before issuing a permit.
|